Town maintained streets are resurfaced cyclically. This year a number of streets will be resurfaced beginning on Thursday, October 19th.
The following streets will be under construction for resurfacing beginning on 10/19/2017 and will be completed in the following order.
Street Name | From- To
1. Prince| King St- End
2. Queen| Barnes St-Prince St
3. King| Barnes St - Prince St
4. William| N Greensboro St- End
5. Lilac| W Poplar Ave- Oleander Rd
6. Oleander| Lynn Dr- Gary Rd
7. Lynn| Oleander Rd- Keith Rd
8. Cathy| Lynn Dr- Gary Rd
9. Keith| Lynn Dr- Gary Rd
10. Gary| W Poplar Ave- End
11. Stratford| Homestead Rd- Autumn Dr
Door Hangers will be distributed on 10/16 for Prince Street. Each street will be notified within 72 hours before work begins.
All streets will remain open during all resurfacing activities. Traffic will be maintained by using flaggers with
Stop and Go paddle boards. Residents will have access to their driveways as the work progresses.
Use Carrboro GIS to look up specific street names and locations: http://gis.ci.carrboro.nc.us/Carrboro/CarrboroGIS/